What we are doing
Works will commence to improve the road surface and encompass extensive patching from Crockenwell, through Drewsteignton to Trennaway Cross between 12 and 23 May.
The work will occur in stages at the following locations:
Stage 1 Beginning of week 1: From Crockenwell heading towards Greystone
Stage 2 Middle of week 1: From Greystone towards the junction with Brierly
Stage 3 End of first week: Drewsteignton close to the village centre
Stage 4 From Drewsteignton village towards Trennaway Cross
Traffic management
The works will be done under a road closure with an official signed diversion.
The road may be open at weekend of 17 and 18 May however this is dependent on the progression of the works.
Access to Castle Drogo throughout the works will be uninterrupted from the A382 (Moretonhampstead to Whiddon Down road).
Diversion route
More information on the road closure and diversion can be found via one. network.