A361 Bishops Tawton Roundabout – Barnstaple


What we are doing

Improvement works on the A361 Bishops Tawton Roundabout in Barnstaple will begin on 3 March 2025. This project aims to ease traffic flow and enhance connectivity in the area.

The scheme will increase capacity on the A361 with additional through lanes and improve pedestrian and cycle links between Bishops Tawton and Barnstaple, including a signal-controlled pedestrian crossing.

This project follows the successful completion of the A39 Westleigh Junction and A39 Buckleigh Road Junction improvements and marks the final scheme of the A361 North Devon Link Road Improvements.

Traffic management

To keep traffic disruption to a minimum, during the hours of 7am to 7pm, a single lane approach to each arm of the roundabout will be maintained. Any works outside these hours may occasionally need for be controlled by manually operated traffic lights.

The works, awarded to Cormac after a competitive tendering process, will last 18 weeks, finishing by early July 2025. Residents and commuters should plan for temporary traffic changes during this period.

Further information

For further information please get in touch.