Essential resurfacing and lining works will take place on the A377 Cowley Bridge, from just north of the junction with St Andrews Road up to and including Cowley Bridge Roundabout, from Tuesday 10 March to Tuesday 24 March 2026.
The works will require the road to be closed between 8pm and 6am on weeknights.
Cowley Bridge roundabout will be open under 3-way temporary traffic lights for the first 4 (approximately) nights to maintain access to A396 Stoke Road and Wrefords Drive.
The roundabout will need to be closed for the last 5 (approximately) nights from 10pm-6am.
These essential works will restore the surface and improve safety for the travelling public. Due to the nature of the works being undertaken they are weather dependent. Any changes to the dates will be shown on the electronic signage present.
The extent of the works area can be seen below in red outlined in black dashes.