Drainage and resurfacing works on the A3072 will begin on Monday 1 September 2025. This work will carry out essential repairs to the existing drainage system and be followed by resurfacing sections of the A23072.
The work will be undertaken in three phases:
Phase One will be drainage works undertaken close to Halsegate Cross to Stone Cross between Monday 1 September and Friday 12 September. The work will be done under convoy working with a reduced speed limit. The road will remain open but delays are to be expected.
Phase Two will be overnight resurfacing works undertaken between the junctions with Crooke Lane and Broadnymett. The road will be closed 7pm to 6am between Monday 15 September and Thursday 24 September and open over the weekend.
Phase Three will be overnight resurfacing between Exbourne Cross and Solland Cross. The road will be closed 7pm to 6am between Thursday 24 September and Wednesday 8 October and open over the weekend.
Access for emergency vehicles will be maintained at all times.