Background
With the recent announcement of the confirmed funding for Exmouth by the Department for Transport and contributions from Devon County Council, East Devon District Council and Exmouth Town Council, this scheme will deliver an extension to link Dinan Way with the A376.
The aim of the works is to reduce congestion along the routes into Exmouth and to provide better access for road users into the town.
What we are doing
The construction of the Dinan Way extension includes:
- installation of a new roundabout and associated works at the junction between Dinan Way and Hulham Road
- installation of a new roundabout and associated works at the junction between A376 and the extension of Dinan Way
- construction of a carriageway, footway and associated works between Hulham Road and the A376

Traffic management
| Scheme | Timescale |
| Dinan Way Extension Main Scheme – Hulham Road Roundabout | Ongoing – finish 14th February 2026 |
| Dinan Way Extension Main Scheme – A376 Roundabout | Ongoing – finish June 2026 |
| A376 Footway widening | Follow on from A376 works, likely commence April – finish June 2026 |
| Summer Lane closure and surfacing (permanent) | Commence late February – finish March 2026 |
| Courtlands Lane surfacing (250m approx.) | Follow on from A376 works, likely commence late April / May 2026 |
| Bus Stop installation and footpath, Hulham Road at Kings Nursery | Commence March – finish April 2026 |
| Hulham Road Drainage maintenance works, Exe View Road and between Dinan Way and Kings Nursery | April 2026 |
| Gorse Lane / Dinan Way traffic signal crossing location and Marley Road / Dinan Way traffic signal crossing location | Ongoing – finish March 2026 |
| Works to improve crossing location and widen footway near Bassetts Farm School | Commence 16th February – finish end of February 2026 |
Diversion route
The overnight diversion route during road closures for resurfacing works will be provided as part of future communications closer to the time of works; our working hours will be 7pm until 7am. Information regarding the diversion route can be found via Causeway one.network
Contact information
For any questions or concerns please get in touch csc.roads@devon.gov.uk