Dinan Way Extension Scheme


Background

With the recent announcement of the confirmed funding for Exmouth by the Department for Transport and contributions from Devon County Council, East Devon District Council and Exmouth Town Council, this scheme will deliver an extension to link Dinan Way with the A376.

The aim of the works is to reduce congestion along the routes into Exmouth and to provide better access for road users into the town.

What we are doing

The construction of the Dinan Way extension includes:

  • installation of a new roundabout and associated works at the junction between Dinan Way and Hulham Road
  • installation of a new roundabout and associated works at the junction between A376 and the extension of Dinan Way
  • construction of a carriageway, footway and associated works between Hulham Road and the A376
Map showing the three stages of works 
A376 Exeter Road - Installation of a new roundabout and associated works at the junction between the A376 and the extension of Dinan Way

Dinan Way - Construction of a carriageway, footway, and associated works between Hulham Road and the A376

 outlined in the previous text

Traffic management

SchemeTimescale
Dinan Way Extension Main Scheme – Hulham Road RoundaboutOngoing – finish 14th February 2026
Dinan Way Extension Main Scheme – A376 RoundaboutOngoing – finish June 2026
A376 Footway wideningFollow on from A376 works, likely commence April – finish June 2026
Summer Lane closure and surfacing (permanent)Commence late February – finish March 2026
Courtlands Lane surfacing (250m approx.)Follow on from A376 works, likely commence late April / May 2026
Bus Stop installation and footpath, Hulham Road at Kings NurseryCommence March – finish April 2026
Hulham Road Drainage maintenance works, Exe View Road and between Dinan Way and Kings NurseryApril 2026
Gorse Lane / Dinan Way traffic signal crossing location and Marley Road / Dinan Way traffic signal crossing locationOngoing – finish March 2026
Works to improve crossing location and widen footway near Bassetts Farm SchoolCommence 16th February – finish end of February 2026

Diversion route

The overnight diversion route during road closures for resurfacing works will be provided as part of future communications closer to the time of works; our working hours will be 7pm until 7am. Information regarding the diversion route can be found via Causeway one.network