Dinan Way Extension Scheme


Installation of a new roundabout and associated works at the junction between Dinan Way and Hulham Road are planned to commence on Monday 23 June 2025.

Traffic management will be via 2-way temporary traffic lights from Monday 11 – Sunday 24 August 2025 between 7pm– 7am for the breakthrough onto the A376. Pedestrian access will be maintained.

Background

With the recent announcement of the confirmed funding for Exmouth by the Department for Transport and contributions from Devon County Council, East Devon District Council and Exmouth Town Council, this scheme will deliver an extension to link Dinan Way with the A376.

The aim of the works is to reduce congestion along the routes into Exmouth and to provide better access for road users into the town.

What we are doing

The construction of the Dinan Way extension includes:

  • installation of a new roundabout and associated works at the junction between Dinan Way and Hulham Road
  • installation of a new roundabout and associated works at the junction between A376 and the extension of Dinan Way
  • construction of a carriageway, footway and associated works between Hulham Road and the A376
Map showing the three stages of works 
A376 Exeter Road - Installation of a new roundabout and associated works at the junction between the A376 and the extension of Dinan Way

Dinan Way - Construction of a carriageway, footway, and associated works between Hulham Road and the A376

 outlined in the previous text

Traffic management

Timescale (2025)Detail
Summer/Autumn3-way lights on Hulham Road (several setups) – Construction of the roundabout
Summer (11th – 24th August)2-way lights nights on the A376 – Cut through earthworks and temporary drainage
AutumnNight road closure for a week – Surfacing of Hulham Road roundabout
Autumn/Winter2-way lights on the A376 – Construction of the roundabout
Winter (January 2026)Night road closure for a week – Surfacing of the A376 roundabout

Diversion route

The overnight diversion route during road closures for resurfacing works will be provided as part of future communications closer to the time of works; our working hours will be 7pm until 7am. Information regarding the diversion route can be found via Causeway one.network