Action Plan

Our Action Plan is produced annually and contains a list of projects which Devon County Council is financially contributing to in 2022/2023. Other risk management authorities in Devon will have their own projects they are contributing to – for more information contact them directly. You can also view the Action Plan on our interactive map.

Devon

Projects/Works/Schemes Lead Authority Study, Design or Works 2022/2023 DCC FRM Contribution £ Revenue 2022/2023 DCC FPW Contribution £ Capital Other External Funding Sources Details of Proposal
Flood Risk Management Team DCC 420,000 Resources required to deliver the Flood Risk Management functions as the Lead Local Flood Authority and Statutory Consultee for SuDS.
Local Flood Improvements and contingency DCC/Others W 100,000 Delivery of  local flood improvement works (subject to resources and in accordance with the DCC priority list and opportunities with other Risk Management Authorities/Local Communities) and an allocation for contingency/risk to support other improvement works.
Property Flood Resilience DCC/Others W 95,000 165,000 Allocation of funds for flood resilience measures through the Property Level Resilience Grant Scheme. Supported with additional £50k Flood Defence Grant in Aid and £20k Local Levy, subject to approval. Including delivery of  Axminster, Harbertonford and South Pool PFR schemes.
Community Resilience and support DCC S/W 25,000 To support delivery and provision of grants through the Devon Community Resilience Forum and to provide assistance to communities for the delivery and provision of Flood Resilience Measures and Emergency Planning.
Natural Flood Management / Working with Natural Processes DCC/Others S/W 125,000 To develop best practice and progress opportunities for delivering natural flood risk management techniques in partnership with other RMAs and key stakeholders, including Northern Devon Nature Based Solutions and East Devon AONB Connecting the Culm projects.
Maintenance of Flood Improvements DCC W 20,000 Maintenance of installed flood improvements, monitoring and guaging equipment

East Devon

Projects/Works/Schemes Lead Authority Study, Design or Works 2022/2023 DCC FRM Contribution £ Revenue 2022/2023 DCC FPW Contribution £ Capital Other External Funding Sources Details of Proposal
Sidmouth Town Centre Surface Water Improvements DCC W 20,000 150,000 550,000 Delivery of surface water drainage improvements in the town centre.
Collaton Raleigh DCC S 10,000 20,000 230,000 Catchment study, consideration of options and delivery of preferrred option of upstream natural flood management and PFR measures
Budleigh Salterton DCC S 10,000 Assessment of flood risk from surface water and ordinary watercourses and consider options for potential improvements and funding opportunities.
Exmouth DCC S 30,000 Assessment of flood risk from surface water and ordinary watercourses and consider options for potential improvements and funding opportunities.
Seaton DCC S 10,000 Assessment of flood risk from surface water and ordinary watercourses and consider options for potential improvements and funding opportunities.

Exeter

Projects/Works/Schemes Lead Authority Study, Design or Works 2022/2023 DCC FRM Contribution £ Revenue 2022/2023 DCC FPW Contribution £ Capital Other External Funding Sources Details of Proposal
Exeter Phase 3 (N’brook P3, Longbrook, Pinbrook, Larkbeare) DCC D 30,000 Carry out investigations for Phase 3 of the surface water management improvements

Mid Devon

Projects/Works/Schemes Lead Authority Study, Design or Works 2022/2023 DCC FRM Contribution £ Revenue 2022/2023 DCC FPW Contribution £ Capital Other External Funding Sources Details of Proposal
Crediton DCC S 10,000 Assessment of flood risk from surface water and ordinary watercourses and consider options for potential improvements and funding opportunities.
Tiverton DCC S 30,000 Assessment of flood risk from surface water and ordinary watercourses and consider options for potential improvements and funding opportunities.

North Devon

Projects/Works/Schemes Lead Authority Study, Design or Works 2022/2023 DCC FRM Contribution £ Revenue 2022/2023 DCC FPW Contribution £ Capital Other External Funding Sources Details of Proposal
Barnstaple DCC S 15,000 15,000 Assessment of flood risk from surface water and ordinary watercourses and consider options for potential improvements and funding opportunities.
Ilfracombe DCC S 10,000 Review of Surface Water Management Plan and potential options

South Hams

Projects/Works/Schemes Lead Authority Study, Design or Works 2022/2023 DCC FRM Contribution £ Revenue 2022/2023 DCC FPW Contribution £ Capital Other External Funding Sources Details of Proposal
Beeson DCC D/W 5,000 100,000 75,000 Scheme to increase culvert capactity in the village and ensure risk is not passed on to others
Totnes DCC S 20,000 Assessment of flood risk from surface water and ordinary watercourses and consider options for potential improvements and funding opportunities.
Dartmouth DCC S 10,000 Initial assessment of flood risk from surface water and ordinary watercourses and consider options for potential improvements and funding opportunities.

Teignbridge

Projects/Works/Schemes Lead Authority Study, Design or Works 2022/2023 DCC FRM Contribution £ Revenue 2022/2023 DCC FPW Contribution £ Capital Other External Funding Sources Details of Proposal
Broadhempston DCC D/W 5,000 80,000 110,000 Detailed design and delivery of PFR focussed flood improvements
Dawlish DCC S 15,000 Assessment of flood risk from surface water and ordinary watercourses and consider options for potential improvements and funding opportunities.
Teignmouth DCC S 10,000 Review of Surface Water Management Plan and potential options
Newton Abbot DCC S 15,000 Assessment of flood risk from surface water and ordinary watercourses and consider options for potential improvements and funding opportunities.

Torridge

Projects/Works/Schemes Lead Authority Study, Design or Works 2022/2023 DCC FRM Contribution £ Revenue 2022/2023 DCC FPW Contribution £ Capital Other External Funding Sources Details of Proposal
Bideford DCC S 15,000 Assessment of flood risk from surface water and ordinary watercourses and consider options for potential improvements and funding opportunities.

West Devon

Projects/Works/Schemes Lead Authority Study, Design or Works 2022/2023 DCC FRM Contribution £ Revenue 2022/2023 DCC FPW Contribution £ Capital Other External Funding Sources Details of Proposal
Okehampton DCC S 15,000 Assessment of flood risk from surface water and ordinary watercourses and consider options for potential improvements and funding opportunities.