Woolsery Primary school Mechanical improvement works

Decision Taken:

Approved

Summary of Reason(s) for Decision Taken:

£30,000 has already been approved for this project at Woolsery Primary school .

Following detailed survey investigation the scope of works was found to be greater than original envisaged . The scheme has been tendered and is considered to represent value for money.

To enable the work to go ahead we are seeking approval for an additional £21,000 that will be funded from the Capital Maintenance Contingency Fund.

Please click on this link

Summary of Alternatives or Options considered and rejected:

None

Details of any conflict of interest and dispensation granted to the Officer taking the decision or by any Member of the Council in delegating responsibility for any specific express delegation:

None

Contact for enquiries/further information:
Chris Dyer Head of Built Environments Email: chris.dyer@devon.gov.uk Tel: 01392 382531
Decision Date:
8 August 2017

A copy of this decision and any supporting documentation considered by the Officer taking this decision may also be made available or inspection by the public at the Council’s Offices or posted upon payment of any copying and postage charges. Any member of the public wishing to take up either of these options is asked to please ring 01392 382888 or email: members.services@devon.gov.uk