Officer Decisions
Chief Officer for Highways, Infrastructure Development and Waste - Meg Booth
St Michael’s C of E Primary School Kingsteignton – Block 01 Roof Improvements
Approved
£62,000 has already been approved for this project at St Michael’s.
Unfortunately this summer appears to be an extremely busy period for roofing contractors and it is difficult to get them to return tender prices. Market forces appear to be forcing the cost of roofing works higher than anticipated and a further £8500 is required for this project. The tender price is still considered to represent value for money.
Approval is sought for an additional £8500, to be funded from the Capital Maintenance Contingency Fund.
None
None
A copy of this decision and any supporting documentation considered by the Officer taking this decision may also be made available or inspection by the public at the Council’s Offices or posted upon payment of any copying and postage charges. Any member of the public wishing to take up either of these options is asked to please ring 01392 382888 or email: members.services@devon.gov.uk