Bolham Primary School – replacement of gas fired boiler:
Approved
Please see link for the authorisation for Capital Budget switch
We are requesting the allocation of an additional £10,000 to the above project funded from the MUMIS Contingency.
The additional costs are as a result of extra work required to correct the pressurisation of the heating system as a result of the failing boiler, which potentially is a health and safety issue.
This additional allocation will bring the total amount allocated to the project to £17,000
None
None
A copy of this decision and any supporting documentation considered by the Officer taking this decision may also be made available or inspection by the public at the Council’s Offices or posted upon payment of any copying and postage charges. Any member of the public wishing to take up either of these options is asked to please ring 01392 382888 or email: members.services@devon.gov.uk