Delayed planning applications

Please provide a list (in Excel format) of all planning applications submitted on or after 2nd October 2013 where no decision was made within 26 weeks (unless a longer period has/had been agreed in writing between the applicant and the Local Authority) and no refund of fees has been made to date. The information should be provided in the following columns:

* Planning application reference
* Applicant name
* Planning application date
* Planning application fee paid (£)
* Decision due date
* Actual decision date
* Extension of time/Planning performance agreed – yes or no?

The information can be seen on this spreadsheet

We should clarify that this information was produced on the assumption that the request is seeking details of planning applications where:
• * No decision was made within 26 weeks AND
• * No longer period for determination had been agreed between the applicant and local authority AND
• * No refund of fees has been made

Within the spreadsheet, where the name has been marked by *, the name of the individual has been withheld as a private individual and is therefore personal information.  This information is exempt from disclosure pursuant to Part 13 of the Environmental Information Regulations 2004.