Devon County Council was one of those awarded money from the Levelling Up Fund for projects in your area.
For each of the projects could you please let me know the following:
Okehampton Interchange (joint agreement with West Devon Borough Council):
1. The status of the project (e.g. yet to start, ongoing, complete)
Rail Station construction substantially complete.
Construction of complementary highway improvements providing access between the station and the highway, including wider active travel links and bus interchange are on site and progressing well.
2. The completion date, or expected completion date
Rail Station is substantially complete but adjacent highway works and processes to enable entry into service expected to be completed in Summer 2026.
3. The amount received from the Levelling Up Fund for the project
£13.455m
4. The remaining funds
£0
Destination Exmouth:
1. The status of the project (e.g. yet to start, ongoing, complete)
Onsite
2. The completion date, or expected completion date
December 2026
3. The amount received from the Levelling Up Fund for the project
£15,765,889
4. The remaining funds
£4,186,628