Chief Officer for Highways, Infrastructure Development and Waste - Meg Booth

Summary of Matter or Issue Requiring Decision:

Two Moors Primary School – Block 01 roof/drainage improvements and Mechanical works

Decision Taken:

Approved

Summary of Reason(s) for Decision Taken:

£28,000 has already been approved for this project at Two Moors Primary School.

The Tenders returned for this work are higher than the previous estimate but are still considered value for money.

To enable this work to go ahead, we are seeking approval for an additional £7,000 that will be funded from the Capital Maintenance Contingency Fund.

http://Please click on Link

Summary of Alternatives or Options considered and rejected:

None

Details of any conflict of interest and dispensation granted to the Officer taking the decision or by any Member of the Council in delegating responsibility for any specific express delegation:

None

Contact for enquiries/further information:
Chris Dyer Head of Built Environments Email: chris.dyer@devon.gov.uk Tel: 01392 382531
Decision Date:
17 July 2017

A copy of this decision and any supporting documentation considered by the Officer taking this decision may also be made available or inspection by the public at the Council’s Offices or posted upon payment of any copying and postage charges. Any member of the public wishing to take up either of these options is asked to please ring 01392 382888 or email: members.services@devon.gov.uk