Officer Decisions
Chief Officer for Highways, Infrastructure Development and Waste - Meg Booth
The Erme Primary School, Ivybridge – Lift Improvement Works
Approved
The sum of £22,000 has already been approved for this project.Following extensive conversations with the proposed lift manufacturer, it has become apparent that additional works are required due to the external nature of where the lift will be positioned. The cost of the additional work is £4,000.Approval is requested to increase the allocation for this project by £4,000 to £26,000 and this will be funded from savings on the heat pump project at Montgomery Primary School.
None
None
A copy of this decision and any supporting documentation considered by the Officer taking this decision may also be made available or inspection by the public at the Council’s Offices or posted upon payment of any copying and postage charges. Any member of the public wishing to take up either of these options is asked to please ring 01392 382888 or email: members.services@devon.gov.uk