1.Why is this work expected to take 3 weeks ?
The works description is “New WPD cable to be installed from BT pole to telemetry box on trash screen trenched across road.” The promoter (Environment Agency) is responsible for planning and identifying the duration of works. The County Council may ‘duration challenge’ the promoter if felt necessary. Further information concerning the technical aspects of the work and its relationship to the duration should be sought from the works promoter. It is worth noting that the promoter has now cancelled these works.
2. What local consultation was there prior to the decision to close the road for three weeks ?
On the application form submitted by the works promoter no information on consultation was provided. The application form is signed by the applicant to declare that; “I have consulted and discussed this closure / restriction(s) with those likely to be affected”.
3. What are the engineering considerations that have led to a solution that requires the road to be closed for 3 weeks ?
Devon County Council do not hold this information. We advise that you contact the Environment Agency.
4. Was any consideration given to alternative solutions ?
Devon County Council do not hold this information.
5. What will be the cost of these particular works?
Devon County Council do not hold this information.
6. Can you please provide details of the role of Neighbourhood Highways Officer
Please refer to this job description