Please could you confirm the below information, relating to the Passivhaus Project completed at:
* Montgomery Primary School – 2011
– Nett construction costs, both;
o During the tender stage:
o At the final account:
– Gross construction costs, both;
o During the tender stage:
o At the final account:
– Delivery programme start – finish dates:
We can confirm the following information:
Net Construction Cost:
Tender: £7,380,381.07
Final Account: £7,543,862
Gross Construction Cost:
Tender: £8,999,218 (works, fees and surveys etc)
Final Account: £9,162,699 (works, fees and surveys etc)
Delivery Programme:
Start (Design): 01/02/2009
Start (Construction): 05/03/2012
Completion: 05/03/2013