Please can you give me a breakdown of all consultancy costs associated with the viability of building a new cycle track on Rifford Road starting on the 11th March 2024 for 52 weeks .
This information can be found at the table below:
2020/21 & FY2021/22 | 2022/23 & FY2023/24 | Total | |||
Feasibility Design & Project Development | Detailed Design & Procurement | ||||
Design | £44,918.06 | £177,105.04 | |||
Survey | £8010.46 | ||||
Procurement | £5568.55 | ||||
Total | £52,928.52 | £182,673.59 | £235,602.11 |