Please could I have the following information:
1) Risk register and costing breakdown of the A380 Kingskerswell Bypass
Please see these links to Volume 1 and 2 of the Full Business Case. Within the Full Business Case you can find the following:
Major Scheme Business Case Full Approval Vol 1
Major Scheme Business Case Full Approval Vol 2
Risk Register – the contractors risks are identified on Page 79 paragraph 6.4.2 of Volume 1. The priced project risk register can be found in Volume 2 Appendix 3.
Costing breakdown – a summary is shown in Table 9 on Page 84 Volume 1. And the breakdown of the contractors costs are in Volume 2 Appendix 2.
2) The post-completion report for the A380 Kingskerswell Bypass?
The report is available at the following link: One Year Monitoring Report [Redacted] (January 2018)