Fines for Overrun Works

Q1. For either street works or road works please state how many times you have fined organisations for overrunning in: (i) 2017/18 (ii) 2018/19 (iii) the current financial year

2017 2018 2019
2 1 4

The information has been collated in calendar years, and the current year (2019) has been taken up to 30 June 2019.

Q2. For each incident state: (i) where the works were (ii) who was fined (iii) when they were scheduled to start and finish and (iv) when they actually finished?

Year Where Who Scheduled Start/Finish Actual Finish
2017 Kingskerswell South West Water 27/03/17 to 30/03/17 18/04/17
Exeter Wales & West Utilities 19/04/17 to 31/05/17 13/06/17
2018 Newton Ferrers Gigaclear 28/06/18 to 02/07/18 10/07/18
2019 Budleigh Salterton Wales & West Utilities 22/03/19 to 11/06/19 20/06/19
Holcombe BT/Openreach 26/04/19 to 30/04/19 14/05/19
Crediton Wales & West Utilities 29/04/19 to 03/06/19 07/06/19
Budleigh Salterton Wales & West Utilities 05/04/19 to 14/06/19 26/06/19

The information has been collated in calendar years, and the current year (2019) has been taken up to 30 June 2019.

Q3. Since 1.4.2017 which street or road works in your area overran by the longest period? Please state: (i) where the works were (ii) who was fined (iii) when they were scheduled to start and finish and (iv) when they actually finished.

Year Where Who Scheduled Start/Finish Actual Finish
2017 Kingskerswell South West Water 27/03/17 to 30/03/17 18/04/17