Cost of roundabout installations

Please include the information for each of the following financial years; 2019/20, 2020/21, 2021/22:
* A list of roundabouts installed by the council including their locations
* The expected budget of each roundabout, when the project was initially begun, and the final cost upon completion

Please only include roundabouts that were completed in these three years and for which figures exist showing the expected budget and the final cost.

We can confirm that the only roundabout which was completed during this time period was Moor Lane roundabout in Exeter.  Please see the following table:

Year Total Revised Budget Final Spend
2019-20 Moor Lane Roundabout, Exeter 1,670,552 682,369
2020-21 Moor Lane Roundabout, Exeter 349,481 32,403
2021-22 Moor Lane Roundabout, Exeter 59,440 59,562