1. I’m looking to get some information about the ongoing road works to replace the gas main on the Bickington Road, can you confirm % of works completed under this first 10-week phase of the project?
Devon County Council (DCC) does not hold this information. In the interests of providing advice and assistance, DCC can confirm that Wales and West Utilities would be most likely to hold this information.
2. Are they on track to finish on time/late/early?
The current phase of works is planned to run until 21 August. No extensions to these dates have been requested at this time.
3. Going forward past this first phase how will the works be managed? Will it be through temp lights or will we have further road closures going forward?
The following phase of works is planned for 24 August to 16 November. Traffic management details for future phases can be viewed on One.Network.