1. What was the cost of the Quickprint roundabout (Whipton Lane/Sweetbrier Lane) modifications as agreed by Devon County Council (DCC)?
£60,000.
2. Please provide the broken down budget versus actual spend and which grant/budget paid for these modifications.
Item | Budget | Actual Cost |
WSP (Design Services) | £17,384.76 | £21,906.88 |
DCC Staff Time | £2,670.01 | £3,543.83 |
Notices | £2,495.90 | £1,606.70 |
Supervision | £0.00 | £901.17 |
Construction | £36,000.00 | £39,513.28 |
Contingency | £1,449.33 | £0.00 |
Total | £60,000.00 | £67,471.86 |
The scheme was funded using:
1. Section 106 (S106) funding from Matford Green and Hill Barton Farm.
2. Local Transport Plan funding from the Casualty and Severity Reduction.
3. Please confirm if there have been any accidents since the roundabout alterations.
There were no injury collisions since the roundabout alterations (December 2022). This data is caveated by noting that this is using unvalidated years of data; is not yet approved by the Department for Transport and therefore is subject to change.