Please provide information and photos relating to pothole D233755033, including initial reporting.
Please refer to this pothole information folder.
The original report made relating to this defect was a member of the public PIP for debris/obstruction, W231582625/D233746051. Debris/obstruction reports on this date were reviewed for action from CSS. A pothole repair – following checks – was instructed, as it was neither an obstruction or debris issue. This instruction was raised on D233755033, and the original D233746051 closed as no further action, with a comment that a pothole instruction had been passed to the contractor.
Station Road, Hemyock
Maintenance Category – 6 local distributor
Willand & Uffculme ED
The original report relating to D233755033:
W231582625 – PIP – 24/01/23
Debris/obstruction
21/02 – Required completion date
24/02 – Actual completion date
Public Comments: ‘Gigaclear/Obelisk trench fill is lifting above road level and breaking up’
D233746051 – CSS
Debris/obstruction
NFA – 24/02/23 (GW)
Reason For No Further Action: Pothole job raised and passed to Contractor for repair
D233755033
Pothole (Safety) – 7 days
Instructed – Milestone – NRT Team
24/03/23 – Instruction date
03/03/23 – Required completion date
01/03/23 – Actual completion date
Reactive comment – 1.4 x .4 – pothole completed.