Impact Assessment Assessment for the Delivery of the DA2 Infrastructure in Dawlish
Dawlish DA2 Infrastructure Delivery – A new 800m link road is proposed extending west from the existing roundabout on the A379 Dawlish (Sainsburys Roundabout) across open land, the proposals include a new highway bridge to span over the Shutterton Brook. The proposed road will assist in unlocking land identified for housing developments.
It should be noted that this project is a Teignbridge District Council (TDC) project that DCC are assisting with the delivery of in regard to the design of a proportion of the road and bridge, procurement and site supervision. The masterplan for the road/bridge has already been undertaken with consultation phases having occurred via TDC. This Impact Assessment has been compiled with this arrangement in mind.
The 800m section of new infrastructure in question is likely to be delivered by three separate parties (Chainage 0-310 by Persimmon Homes, Chainage 310-440 by TDC/DCC, Chainage 440-800 by Designed Adpad, Constructed DCC), each party has or will seek their own Planning Consent.
Funding achieved by TDC will contribute to each of the three development sections.