Work started in spring 2021 and is due to be completed in spring 2023. The following schedule is subject to change:
Date | Work starting |
---|---|
Spring 2021 | Enabling works, site preparation and mobilisation |
Summer 2021 |
Signalling Platform substructures – includes excavation of the foundations, piling and forming the concrete bases. Bridge foundations |
Autumn 2021 |
Platform superstructures – includes installation of platform cantilever beams, precast slabs, platform coping and litter guards. Approach ramps – includes stabilisation of the existing embankment, construction of retaining wall to build up the new ramps, as well as laying kerbs, surfacing material and handrails. |
Winter 2021 |
Footbridge installation Platform finishes |
Spring 2022 | Platform accesses |
Summer 2022 | Mechanical and electrical works |
Autumn 2022 & Winter 2022/23 | Access and approach ramp finishes along with testing and commissioning |
Winter 2022/23 | Construction work complete and bridge opens to public |
Summer 2023 | Station opens |