Roadworks

A361 North Devon Link Road – new junction for east of Tiverton and Challenge Fund resurfacing scheme

Phase one of the new junction on the A361 for the Tiverton Eastern Urban Extension was completed in summer 2018. More information can be found on our News centre.


Challenge Fund resurfacing scheme

The scheme involves resurfacing of both carriageways, waterproofing two bridges, drainage work, replacement of signs and vehicle restraint systems, the management of the trees, scrub and grassed areas adjacent to the highway and other minor works.

Traffic management

The remaining traffic management will involve single lane closures (although work is subject to weather conditions).

  • Monday 29 April – Overnight closure of eastbound lane 2
  • Tuesday 30 April – Overnight closure of westbound lane 1

The speed limit will be temporarily reduced to 40 mph to protect members of the public and the workforce and the laybys within the extent of the work will be temporarily closed.

Information can also be found on the Mildren Construction project website.

Funding

The scheme is being funded through the Challenge Funding Scheme.

More information

Mildren Construction Ltd is the appointed contractor for this work and more information, including contact details, is available on its dedicated website A361.today.