B3327 between Watergate Bridge and Stibb Cross and the junction with A388 at Stibb Cross

What we are doing

Patching, covering, kerbing, drainage, and overlay work will take place in 4 phases on B3327 between Watergate Bridge and Stibb Cross and the junction with A388 at Stibb Cross. 4 road closures will occur between 5-30 June.

The Phase 3 works are anticipated to have the largest impact on the surrounding area however this will be minimised where possible.

Traffic management

Phase 1 – 5-14 June –  Patching Works – B3327 Watergate Bridge to Dragon Hill – 24-Hour Closure

The works will be carried out under a 24-hour road closure including weekends. Access to Langtree will be maintained from Stibb Cross and for school buses.

Phase 2 – 19-23 June – Patching Works – B3227 Stibb Cross to Langtree Village entrance – 24-Hour Closure

The works will be carried out under a 24-hour road closure. Access to Langtree will be maintained from Stibb Cross and for school buses.

Phase 3 – 26-27 June – Various Works – Junction of B3227 and A388 Stibb Cross – 0800-1800

The works will be carried out under a road closure between 0800-1800 to address issues with covers, kerbing, and drainage. Access from Shebbear will not be possible into the junction. Access for school buses will be maintained.

Phase 4 – 28-30 June – Overlay Works – B3227 for 120m from the junction with A388

The works will be carried out under a 24-hour road closure. Access to school buses will be maintained. 

Diversion route

There will be a signed diversion route in place for all phases.

More information can be found on one.network

 