B3217 High Bickington

What we are doing

There will be roadworks starting on the B3217 through High Bickington, starting on Monday 8 August. These roadworks will allow for drainage and resurfacing works to take place.

Road closures

  • 8 -12 August the road will be closed from Weeks Cross to High Bickington. This closure is for drainage works to take place. Works will start at the Dolton Beacon end of the road.

The road will be reopened on weekend of 13 -14 August.

  • 15 August the road will be closed again to allow reconstruction works to take place in the heart of the village from the Golden Lion to Pound Lane.

These works will be completed and the road reopened over the weekend of 20 – 21 August.

  • 22 August – 5 September including weekends from Weeks Cross to High Bickington. Drainage and patching works will be completed.┬áThis will conclude the works.

Diversion route

The diversion route for the closure can be found via one.network

Local traffic

Access to High Bickington village from the North via the A377 and Atherington will be maintained during the closures and signed.

On 27 August access to the fete will be maintained. This will be from Atherington through High Bickington, to the fete showground in Quarries Lane.