A3072 Dunsland Cross, Garlands Moor, Golden Inn, Greenslade to De Bathe Cross

What we are doing

Between 22 March and 25 May 2021 planned highway resurfacing and drainage works will be carried out at four locations on the A3072.

The type of work being undertaken and the traffic management which is necessary for the works to be carried out and which will be encountered by highway users. The webpage will be updated regularly.

These areas are:

  • Golden Inn
  • Garlands Moor
  • Dunsland Cross
  • Greenslade to De Bathe Cross

The drainage works will be carried out during the day under lane closures and the resurfacing work under road closures at night

Area Dates Diversion
Dunsland Cross 5 April – 27 April

Red shows road closure, purple shows diversion route
Red shows road closure, purple shows diversion route
Golden Inn 6 April – 16 April

Red shows the road closure, purple shows diversion route
Garlands Moor 16 April – 7 May

Red shows road closure, purple shows diversion route
Greenslade 29 April – 21 May

Red shows road closure, purple shows diversion route

Why we have to close the highway

Traffic management is needed due to the nature of the works being undertaken and for the safety of the public.

The majority of the work will be done under road closures at night in order to maintain the road open for as long as possible.