Phase 2: Pinhoe Road and Exhibition Way – March and April 2020

The work at the Pinhoe Road and Exhibition Way junction were completed (except for the surfacing).

The temporary signals were removed, and the new permanent signals were switched on in the middle of March. As the work on Exhibition Way is not complete, the traffic signals are currently not working at their optimum. Once the junction has been resurfaced, the operations of the traffic signals will be optimised.

Work has started on both sides of Exhibition Way and will move further north towards Pinbrook Road as the scheme progresses.

In the next two months, and subject to availability of materials, it is planned that work on the west side of Exhibition Way will be completed to allow the work on the east side of Exhibition Way between Aldi and Pinbrook Road to start. Work will also start on the south side of Pinhoe Road, to the east of Bakers Way.

The full road closures of Pinhoe Road and Exhibition Way, including the side roads Pinbrook Road, Aldi junction and Bakers Way, are currently planned to start the first week of June for three weeks. These closures will be undertaken at night time only between 7:00 pm and 6:00 am and a signed diversion route will be provided where possible.

This work is dependent on surfacing materials which are not currently available because batching plants are not open.

Work schedule

The schedule below provides an overview of how the work on Exhibition Way and Pinhoe Road is progressing. These dates and timeframes are indicative and will be updated as the scheme progresses.

Work phasePlanned date of work (2020 unless stated)Progress
East side of Exhibition Way north of SummerwayDecember 2019Complete, except for the footway surfacing and street lighting
Compound set upWeek commencing 6 JanuaryComplete
South side of Pinhoe Road from Bakers Way to the junction with Exhibition WayJanuary/FebruaryComplete, except for the footway surfacing and street lighting
East side of the junction between Pinhoe Road and Exhibition WayJanuary/FebruaryComplete, except for the footway surfacing and street lighting
Exhibition Way, east side, opposite SummerwayJanuary/FebruaryComplete, except for the footway surfacing and street lighting
West side of the junction between Pinhoe Road and Exhibition WayMarchComplete, except for the footway surfacing
Exhibition Way west side between Pinhoe Road and Aldi junctionFebruary/MarchComplete, except for the footway surfacing and street lighting
Exhibition Way west side between Aldi junction and Pinbrook Road junctionMarch/MayOngoing
Exhibition Way east side between Pinhoe Road and Aldi junctionMarch/AprilOngoing
Exhibition Way east side between Aldi junction and Pinbrook Road junctionApril/JuneNot started
Pinhoe Road south side between Pilton Lane and Bakers WayApril/JuneNot started
Exhibition Way, east side, north of Pinbrook Road up to SummerwayJuneNot started
Resurfacing workJuneNot started
Remove the site compoundEnd of JuneNot started