The main construction work was started on Monday 6 January 2020 opposite Summerway and on the south side of Pinhoe Road.
Work in the north-east corner of the Pinhoe Road and Exhibition Way junction were completed and reopened to the public during the last week of February.
Traffic signals across Exhibition Way were removed and replaced by temporary traffic signals. These include signal-controlled pedestrians’ crossings and will remain operational until the new permanent signals are installed in mid-March.
Work on the west side of Exhibition Way started at the end of February and will continue through March. This section of work is to enable the carriageway to be realigned so that the improved cycle path can be constructed on the eastern side.
Work to the central island on Pinhoe Road, also started at the end of February which will enable the installation of the toucan crossing in this location. Work on this section is expected to finish at the beginning of March.
During the next two months, work will move along Exhibition Way, first on the west side then once the carriageway is realigned, on the east side.
Work schedule
The schedule below provides information on planned and completed work for Exhibition Way and Pinhoe Road. Dates and timescales are indicative and will be updated as the scheme progresses.
Work phase | Planned date of work (2020 unless stated) | Progress |
East side of Exhibition Way north of Summerway | December 2019 | Complete, except for the footway surfacing and street lighting |
Compound set up | Week commencing 6 January | Complete |
South side of Pinhoe Road from Bakers Way to the junction with Exhibition Way | January/February | Complete, except for the footway surfacing and street lighting |
East side of the junction between Pinhoe Road and Exhibition Way | January/February | Complete, except for the footway surfacing and street lighting |
Exhibition Way, east side, opposite Summerway | January/February | Complete, except for the footway surfacing and street lighting |
West side of the junction between Pinhoe Road and Exhibition Way | March | Not started |
Exhibition Way west side between Pinhoe Road and Aldi junction | February/March | Ongoing |
Exhibition Way west side between Aldi junction and Pinbrook Road junction | March/May | Not started |
Exhibition Way east side between Pinhoe Road and Aldi junction | March/April | Not started |
Exhibition Way east side between Aldi junction and Pinbrook Road junction | April/June | Not started |
Pinhoe Road south side between Pilton Lane and Bakers Way | April/June | Not started |
Exhibition Way, east side, north of Pinbrook Road up to Summerway | June | Not started |
Resurfacing work | June | Not started |
Remove the site compound | End of June | Not started |