Essential repair works to the underside of the bridge deck on the Countess Wear Flood Relief Bridge are to be undertaken from 22:00 hours on Friday 28 October to 05:00 hours on Monday 31 October, during which time the road … Continue reading
Exeter
-
-
Progress Report 2
Progress Report 2 – 26th April to 27th May 2016: Welcome to the second instalment of our series of progress reports on the Civil Engineering works at Bridge Road, Exeter. As work has begun on a variety of structures, this latest … Continue reading
-
Overnight temporary lights on Bridge Road
Temporary traffic lights will be introduced overnight on Bridge Road in Exeter tomorrow evening (Thursday 28 April). From 11pm on Thursday until 5am on Friday morning, traffic lights will be in place on a short length of the road over … Continue reading
-
Progress Report 1
Welcome to the first of a series of reports on the civil engineering works ongoing at Bridge Road, Exeter. Each report will briefly explain the work that’s occurred since the previous report, and will include areas not visible from the … Continue reading
-
Fly-through of Bridge Road
Devon County Council has released a fly-through video and aerial photographs of Bridge Road, Exeter, capturing the route at the start of the on-going improvement scheme Continue reading
-
Opening of Canal Bridges in Exeter
The Canal Bridges in Exeter will be opened at 11am on Wednesday (9 March) Continue reading
-
Overnight closure at Bridge Road not needed tonight
Planned overnight closures are not required tonight as traffic management arrangements to make the road one lane in each direction were completed last night Continue reading
-
Bridge Road overnight closures
Bridge Road will be closed overnight on Monday 22 February and Tuesday 23 February, from 10pm to 5am to enable site staff to safely establish the traffic management to reduce the road to one lane each way Continue reading