Bickington Road Works
=====================

**1. I’m looking to get some information about the ongoing road works to replace the gas main on the Bickington Road, can you confirm % of works completed under this first 10-week phase of the project?**

Devon County Council (DCC) does not hold this information. In the interests of providing advice and assistance, DCC can confirm that [Wales and West Utilities](https://www.wwutilities.co.uk/) would be most likely to hold this information.

**2. Are they on track to finish on time/late/early?**

The current phase of works is planned to run until 21 August. No extensions to these dates have been requested at this time.

**3. Going forward past this first phase how will the works be managed? Will it be through temp lights or will we have further road closures going forward?**

The following phase of works is planned for 24 August to 16 November.  Traffic management details for future phases can be viewed on [One.Network](https://one.network/).