Road Park Bridge Barnstaple
===========================

**Please provide the following information:**
**1. Full details of all engineering inspections and assessments carried out prior to the painting of the superstructure of Rock Park Bridge, Barnstaple in 2016/17.**

General Inspection – 3/7/2013. There was no report on this inspection, however photos can be found in the following folder [Rock Park Bridge General Inspection](https://devoncc.sharepoint.com/:f:/s/PublicDocs/InfoMgt/Es09Vk0lvM1HvOEgDuAWmOsBWZoZkMSOKapQJ7NGzqlMgg?e=WUBDbG).

Principal Inspection – 14/14/2015. The report for this can be found at the following link [Rock Park Bridge Principal Inspection](https://devoncc.sharepoint.com/:b:/s/PublicDocs/InfoMgt/EdgHPL_HnqFMnogVn7zphaEBRoFoBNmrT62MFEdrRoqzdw?e=kZcYe8)..

Information that has been greyed out is exempt from disclosure under Section 40(2) of the Freedom of Information Act 2000 (Personal Data).

The Council cannot disclose personal information if releasing it would contravene any of the provisions in the UK General Data Protection Regulation. In this instance release of this information would contravene the first data protection principle and therefore the information is withheld

Please note we do not have any inspection details pre 2013.

**2. Full details and costs of all engineering inspections and assessments associated with Rock Park Bridge in Barnstaple from the completion of the superstructure painting in 2016/17 to the current day.**

Engineering inspection/assessmentDateCostVarious inspections relating to the repainting works2016-2018Cost information not held – staff time paid from a general budgetGeneral inspection04/04/2019Cost information not held – staff time paid from a general budgetDive inspection – snorkel04/05/2020Cost information not held – staff time paid from a general budgetDive inspection – full dive07/05/2020£2,547.11Geotechnical investigations, boreholes and loggingJuly 2020£9,750.00Examination of metal samplesJuly 2020£150.00Preliminary structural assessment including technical noteAugust 2020£639.83Topographic surveySeptember 2020£846.00Ground investigation – riverbed materialMay 2022£1,277.50Principal inspectionOctober 2022Cost information not held – staff time paid from a general budgetSonar survey of riverbed20/04/2023£5,700

**3. Full details and costs of the engineering work, associated interventions and safety work carried out from the date of the emergency closure, to the completion of the restoration project.**

Works costs

Including: Closing the bridge and installation of fencing, temporary diversion route and signs; vegetation clearance; investigations and surveys; main stabilisation works which involved installation of a temporary support system, construction of pier repairs, removal of the temporary support system, resurfacing of the deck and repairs to the timber deck planks.

£3,007,905

Design costs

Including: Staff time including carrying out the design of the repair and production of contract documentation and drawings; specialist advice including geotechnical, ecological and structural engineering consultation; obtaining the necessary licences and land access agreements; carrying out surveys, investigations and materials testing.

£156,423

Supervision costs

Including: Staff time to conduct site supervision of the works; management of the contract and quality management.

£37,562TOTAL:£3,201,890

**4. Details of the type, frequency and anticipated dates of future inspections to ensure the continued integrity and safety of this much loved, well used, historically and architecturally significant asset.**

General Inspection every 2 years (next due 2024)
Dive or Sonar inspection every 2 years (next due 2025)
Principal Inspection every 6 years (next due in 2028)