**1. What was the cost of the Quickprint roundabout (Whipton Lane/Sweetbrier Lane) modifications as agreed by Devon County Council (DCC)?**

£60,000.

**2. Please provide the broken down budget versus actual spend and which grant/budget paid for these modifications.**

ItemBudgetActual CostWSP (Design Services)£17,384.76£21,906.88DCC Staff Time£2,670.01£3,543.83Notices£2,495.90£1,606.70Supervision£0.00£901.17Construction£36,000.00£39,513.28Contingency£1,449.33£0.00Total£60,000.00£67,471.86

The scheme was funded using:

1\. Section 106 (S106) funding from Matford Green and Hill Barton Farm.

2\. Local Transport Plan funding from the Casualty and Severity Reduction.

**3. Please confirm if there have been any accidents since the roundabout alterations.**

There were no injury collisions since the roundabout alterations (December 2022). This data is caveated by noting that this is using unvalidated years of data; is not yet approved by the Department for Transport and therefore is subject to change.