Honiton Road Manhole Cover Repairs
==================================

**1. Works have recently been undertaken on Honiton Road in relation to a manhole cover. Please provide a timeline of those works.**

**Time (24hours)****Date****Information**15:3517/09/23Report received from the police regarding blown gully/chamber covers on Honiton Road.15:4217/09/23Information passed to contractor to attend site and make safe with traffic management.16:2717/09/23Council contractor attended and apparatus identified as South West Water (SWW) owned. Details passed to SWW.AM18/09/23Council enforcement officer contacted SWW, who initially attend the site.PM18/09/23SWW advised officer of potential chamber/frame damage requiring investigation and a fix.18:3120/09/23SWW attended and set up traffic management, adopting responsibility for the site.08:4421/09/23SWW raised immediate (urgent) works permit with the Council.09:3521/09/23Permit granted.10:4221/09/23SWW requested by the Council to ensure manual control of the temporary lights 07:00-19:00hrs.11:3621/09/23SWW added a condition to permit signifying manual controls.13:3521/09/23Change to permit with added condition granted.16:4725/09/23The Council requested prompt completion of SWW works due to congestion and public representations.09:1226/09/23SWW records that works have stopped.14:4027/09/23SWW records site registration submitted for inspection.

**2. What caused a delay to its permanent fixing?**

Some delay was experienced due to the volume of incidents arising with SWW and resource availability following the poor weather.  Following the fix and reinstatement of the road a period of 24 hours is required for materials to cure, before the road could be reopened.

 **3. Was this issue delegated to a contractor?**

SWW is the responsible for the works. They are the statutory undertaker and owner of the apparatus. SWW use Kier Group Plc as their works contractor.