Bridge Maintenance 2021/2022
============================

**The questions below relate to the financial year 2021/2022**

**1. How many road bridges are you responsible for maintaining?**

2714

**2. (i) how many Principal Inspections have taken place?**

28

**(ii) how many Principal Inspections did you plan to do?**

35

**3. (i) how many General Inspections have taken place?**

1041

**(ii) how many General Inspections did you plan to do?**

1361

**4. How many Structural Reviews did you undertake?**

28

**5. How many sub-standard (in terms of capacity) and/or weight restricted bridges do you have?**

224

**6. Of these, how many do you intend to return to full load carrying capacity in the next 5 years?**

3

**7. How many bridges would you return to full load carrying capacity if you had no resource restrictions?**

83

**8. (i) How many post-tensioned bridges do you have?**

27

**(ii) How many of those have had Post Tensioned Special Inspections (PTSI) within the last 18 years?**

15

**(iii) Of those that have not had a PTSI, how many require/are due one?**

9

**(iv) How much funding would you anticipate is required to remove the backlog of PTSIs for those bridges identified in Q8(iii)?**

£0.65m

**9. In monetary terms, what is the current depreciation?**

£455,693,008

**10. What is the calculated value of your work bank?**

We do not hold this calculation.

**11. (i) What is the annual revenue works budget for maintaining your bridge stock? (excluding staff costs)**

£66,000

**(ii) What is the annual capital works budget for maintaining your bridges stock?**

£9,000,000

**(iii) What total budget would you estimate is required to maintain the bridge stock at its current level (standstill budget)?**

£8,000,000

**12. (i) How many Stage 1 Scour Assessments did you undertake as a % of those requiring an assessment?**

0.2%

**(ii) How many Stage 2 Scour Assessments did you undertake as a % of those requiring an assessment?**

2.87%

**13. (i) How many bridges under your management completely collapsed?**

0

**(ii) How many bridges under your management partially collapsed?**

0

**(iii) Would you be happy to share the detail with members of the UK Bridges Board?**

Yes

**14. What was your Bridge Stock Condition Index (BSCI) at the end of 2021/2022 (or current if easier)?**

We do not hold this calculation.

**15. What issues with managing your bridge stock causes you most concern?**

A shortage of engineers, particularly experienced Chartered or Incorporate engineers, and losing engineers to National Highways who can offer significantly higher salaries than Local Government.