Traffic modelling
=================

In planning for this next phase of work, traffic simulation technology has been used to model the local area and assess the potential impact on traffic for road users through temporary traffic lights and road closures with diversions.

The modelling showed that the solution which resulted in the least disruption was to carry out construction using road closures with two diversion options. These diversions will allow traffic flow to be quicker and more reliable than waiting to get through multiple sets of temporary traffic lights.

The tables below shows the anticipated journey times associated with the different phases and scenarios for traffic management:

### Anticipated journey times for each travel option

#### Closure at Jetty Marsh/Whitehills Cross

ScenarioVia A382Via A382/B3193Via A383**Length****Average time****Average speed****Length****Average time****Average speed****Length****Average time****Average speed**Whole scheme on traffic lights4.6 km26 minutes7 mph14.4 km18 minutes30 mph12.0 km13 minutes34 mphNormal closureClosedClosedClosed14.4 km31 minutes17 mph12.0 km13 minutes34 mphDigital closure with VMSClosedClosedClosed14.4 km29 minutes19 mph12.0 km13 minutes34 mph

#### Closure at Forches Cross

ScenarioVia A382Via A382/B3193Via A383**Length****Average time****Average speed****Length****Average time****Average speed****Length****Average time****Average speed**Whole scheme on traffic lights4.6 km26 minutes7 mph14.4 km18 minutes30 mph12.0 km13 minutes34 mphNormal closureClosedClosedClosed14.4 km22 minutes24 mph12.0 km13 minutes34 mphDigital closure with VMSClosedClosedClosed14.4 km20 minutes27 mph12.0 km13 minutes34 mph